The Town and Country Planning (Fees for Applications and Deemed Applications) (Scotland) Amendment Regulations 1991

Regulation 2(3)(d)

SCHEDULE

TABLE

12
(Category of development)(Fee payable)
I. Operations

1.  The erection of dwellinghouses (other than development within category 5).

Where the application is for–

(a)

outline planning permission, £92 for each 0.1 hectare of the site area, subject to a maximum of £2,300; or for one dwellinghouse £92;

(b)

Other than outline planning permission, £92 for each dwellinghouse to be created by the development, subject to a maximum of £4,600.

2.  The erection of buildings (other than buildings coming within category 1, 3 or 5).

Where the application is for–

(a)

outline planning permission, £92 for each 0.1 hectare of the site area, subject to a maximum of £2,300;

(b)

other than outline planning permission–

(i)

where no floor space is to be created by the development, £46;

(ii)

where the area of gross floor space to be created by the development does not exceed 40 square metres, £46;

(iii)

where the area of gross floor space to be created by the development exceeds 40 square metres but does not exceed 75 square metres, £92; and

(iv)

where the area of gross floor space to be created by the development exceeds 75 square metres, £92 for each 75 square metres, subject to a maximum of £4,600.

3.  The erection on land used for the purposes of agriculture, of those buildings excluded by virtue of sub-paragraph (c) in paragraph (1) of class V in Schedule 1 to the General Development Order from that class.

(a)Where the application is for outline planning permission, £92 for each 0.1 hectare of the site area, subject to a maximum of £2,300;

(b)In all other cases–

(i)where the area of gross floor space to be created by the development does not exceed 465 square metres, nil;

(ii)where the area of gross floor space to b e created by the development exceeds 465 square metres but does not exceed 540 square metres, £92;

(iii)where the area of gross floor space to be created by the development exceeds 540 square metres, £92 for the first 540 square metres and £92 for each 75 square metres in excess of that figure subject to a maximum of £4,600.

4.  The erection, alteration or replacement of plant or machinery.

£92 for each 0.1 hectare of the site area, subject to a maximum of £4,600.

5.  The enlargement, improvement or other alteration of existing dwellinghouses.

(a)Where the application relates to one dwellinghouse, £46;

(b)where the application relates to 2 or more dwellinghouses, £92.

6.(a) The carrying out of operations, including the erection of a building, within the curtilage of an existing dwellinghouse, for purposes ancillary to the enjoyment of the dwellinghouse as such;

(b)the erection or construction of gates, fences, walls or other means of enclosure along a boundary of the curtilage of an existing dwellinghouse; or

(c)the construction of car parks, service roads and other means of access on land used for the purposes of a single undertaking, where the development is required for a purpose incidental to the existing use of the land.

£46

7.  The carrying out of any operations connected with exploratory drilling for oil or natural gas.

£92 for each 0.1 hectare of the site area, subject to a maximum of £6,900.

8.  The carrying out of any operations not within categories 1 to 7.

In the case of operations for–

(a)

the winning and working of minerals, £46 for each 0.1 hectare of the site area, subject to a maximum of £6,900;

(b)

the winning and working of peat, £46 for each hectare of the site area, subject to a maximum of £690;

(c)

any other purpose, £46 for each 0.1 hectare of the site area, subject to a maximum of £460.

II. Uses of Land

9.  The change of use of a building to use as one or more separate dwellinghouses.

£92 for each additional dwellinghouse to be created by the development, subject to a maximum of £4,600.

10(a) The use of land for the disposal of refuse or waste materials or for the deposit of material remaining after minerals have been extracted from land: or

(b)the use of land for the storage of minerals in the open.

£46 for each 0.1 hectare of the site area, subject to a maximum of £6,900.

11.  The making of a material change in the use of a building or land, other than a material change of use within category 9 or 10.

£92

12.  The continuance of a use of land, or the retention of buildings or works on land, without compliance with a condition subject to which a previous planning permission has been granted, including a condition requiring the discontinuance of the use or the removal of the building or works at the end of a specified period.

£46.