SCHEDULE 2

Specifications of the road bridge which crosses the northern end of the Selby Canal south east of Brayton in the County of North Yorkshire.

Points of Commencement and Termination

From a point on the north western bank of Selby Canal approximately 158 metres south west of the north east corner of OS Parcel 8119 (reference Point A on Plan B).

To a point on the south eastern bank of Selby Canal approximately 240 metres south west of the dwelling "Sal-Que-Sun', Brayton Lane (reference Point B on Plan B).

Length

Total length between abutments is not less than 61 metres measured along the centre line of the new road comprising:–

One fixed span of not less than 20 metres measured along the centre line of the new road.

One fixed span of not less than 41 metres measured along the centre line of the new road.

Headroom and Waterway

navigational airdraught of not less than 5.5 metres above water level over a navigational channel not less than 20 metres wide, measured at right angles to the centre line of the canal.

Plan A–Key Plan.

Plan B–Plan of Bridge.

Plan C–Elevation of Bridge.