37.—(1) This regulation applies where—
(a)a sub-contractor’s tax certificate is issued in the form specified in paragraph (5) of regulation 24, and
(b)a contract payment is made to the company without the deduction imposed by section 559.
(2) Where this regulation applies, a user who is a director or the secretary of the company shall, for every contract payment made to the company, give a voucher in the form numbered 715 in Schedule 1, completed and signed by him in accordance with regulation 38, to the contractor upon or not later than seven days after receipt of any such payment.
(3) A contractor shall make every effort reasonable in the circumstances to obtain such a voucher in respect of every such payment made by him.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: