6. In the course of any evaluation made for the purpose of deciding who should undertake or carry out the work the local authority shall take into account in the manner prescribed in these Regulations—
(a)the particulars of the bid referable to the amount which would be credited to the account of the direct service organisation for the performance of the work, and the particulars of each contractor’s tender referable to the fees and expenses which would be payable to the contractor for the performance of the work;
(b)where the local authority requires the contractor to provide particulars of a bond or guarantee in relation to the performance of the work, the cost quoted by each contractor or providing a bond or guarantee which meets the requirements of the invitation to tender for the work;
(c)the present value of savings;
(d)the total amount of allowable costs included by the local authority in the bid;
(e)the total amount of prospective costs calculated or estimated by the local authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: