The Railways and Other Transport Systems (Approval of Works, Plant and Equipment) Regulations 1994

Relevant operational limitations

9.  An application for approval which—

(a)states any relevant operational limitation which is intended to be imposed on the use of the new works, plant or equipment or the altered works, plant or equipment which are the subject of the application; or

(b)is accompanied by a certificate under regulation 7 that the plant or equipment or, as the case may be, any plant or equipment incorporated into the works or alterations, which are the subject of the application, conforms with a prototype which has been approved to be used subject to any relevant operational limitation,

shall be construed as an application for approval for the new works, plant or equipment or the altered works, plant or equipment to be brought into use subject to that relevant operational limitation.