Citation, commencement and extent1

These Regulations may be cited as the Urban Waste Water Treatment (England and Wales) Regulations 1994, shall come into force on 30th November 1994 and shall extend to England and Wales.

Interpretation2

1

In these Regulations, unless the context otherwise requires—

  • “agglomeration” means an area where the population and/or economic activities are sufficiently concentrated for urban waste water to be collected and conducted to an urban waste water treatment plant or to a final discharge point;

  • “the Authority” means the National Rivers Authority;

  • “coastal waters” means the waters outside the low-water line or the outer limit of an estuary;

  • “collecting system” means a system of conduits which collects and conducts urban waste water;

  • “the Directive” means Council Directive 91/271/EEC concerning urban waste water treatment M1, and references to other Community Directives are references to Directives other than Council Directive 91/271/EEC;

  • “domestic waste water” means waste water from residential settlements and services which originates predominantly from the human metabolism and from household activities;

  • “estuary” means the transitional area at the mouth of a river between fresh-water and coastal waters, the outer (seaward) limits of which are shown on maps kept in accordance with regulation 12;

  • “eutrophication” means the enrichment of water by nutrients, especially compounds of nitrogen and/or phosphorus, causing an accelerated growth of algae and higher forms of plant life to produce an undesirable disturbance to the balance of organisms present in the water and to the quality of the water concerned;

  • “high natural dispersion area” has the meaning given by regulation 3;

  • “industrial waste water” means any waste water which is discharged from premises used for carrying on any trade or industry, other than domestic waste water and run-off rain water;

  • “population equivalent” is a measurement of organic biodegradable load, and a population equivalent of 1 (1 p.e.) is the organic biodegradable load having a five-day biochemical oxygen demand (BOD5) of 60g of oxygen per day (the load shall be calculated on the basis of the maximum average weekly load entering the treatment plant during the year, excluding unusual situations such as those due to heavy rain);

  • “secondary treatment” means treatment of urban waste water by a process generally involving biological treatment with a secondary settlement or other process in which the requirements established in Table 1 in Schedule 3 are respected;

  • “sensitive area” has the meaning given by regulation 3;

  • “sludge” means residual sludge, whether treated or untreated, from urban waste water treatment plants;

  • “urban waste water” means domestic waste water or the mixture of domestic waste water with industrial waste water and/or run-off rain water;

and other expressions used in the Directive have the same meaning as in the Directive.

2

Any reference in these Regulations to a numbered regulation or Schedule is a reference to the regulation or Schedule so numbered in these Regulations.

Annotations:
Marginal Citations
M1

OJ No. L 135, 30.5.91, p. 40.

Sensitive areas and high natural dispersion areas3

1

F1Subject to regulation 2 of the Urban Waste Water Treatment (England and Wales) (Amendment) Regulations 2003, in these Regulations—

a

“sensitive area” means an area of water which the Secretary of State has identified in accordance with the criteria set out in Part I of Schedule 1, and which is shown as such on maps deposited with the Authority for the purposes of this regulation;

b

“high natural dispersion area” means an area of water which the Secretary of State has identified in accordance with the criteria set out in Part II of Schedule 1, and which is shown as such on maps deposited with the Authority for the purposes of this regulation.

2

The Secretary of State shall review the identification of sensitive areas and high natural dispersion areas, in accordance with the relevant criteria in Schedule 1, no later than 31st December 1997 and thereafter at intervals of no more than four years.

F23

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Duty to provide and maintain collecting systems and treatment plants4

1

This regulation supplements the duty imposed on every sewerage undertaker by section 94 of the Water Industry Act 1991 M2 (general duty to provide sewerage system) and any contravention of the requirements of this regulation shall be treated for the purposes of that Act as a breach of that duty.

2

Subject to paragraph (3) below, the duty imposed by subsection (1)(a) of the said section 94 shall include a duty to ensure that collecting systems which satisfy the requirements of Schedule 2 are provided—

a

where the urban waste water discharges into receiving waters which are a sensitive area, by 31st December 1998 for every agglomeration with a population equivalent of more than 10,000; and

b

without prejudice to sub-paragraph (a) above—

i

by 31st December 2000 for every agglomeration with a population equivalent of more than 15,000; and

ii

by 31st December 2005 for every agglomeration with a population equivalent of between 2,000 and 15,000.

3

Paragraph (2) above shall not apply where either—

a

the Authority has certified that the establishment of a collecting system is not justified because it would produce no environmental benefit; or

b

the Secretary of State has certified that the establishment of a collecting system is not justified because it would involve excessive cost,

and individual systems or other appropriate systems are provided and the Authority has certified that those systems achieve the same level of environmental protection.

4

The duty imposed by subsection (1)(b) of the said section 94 shall include a duty to ensure that urban waste water entering collecting systems is, before discharge, subject to treatment provided in accordance with regulation 5, and to ensure that—

a

plants built in order to comply with that regulation are designed (account being taken of seasonal variations of the load), constructed, operated and maintained to ensure sufficient performance under all normal local climatic conditions;

b

treated waste water and sludge arising from waste water treatment are reused whenever appropriate; and

c

disposal routes for treated waste water and sludge minimise the adverse effects on the environment.

Requirements as to provision of treatment5

1

Subject to paragraph (5) below, treatment plants which provide secondary treatment or an equivalent treatment shall be provided—

a

by 31st December 2000 or, in an exceptional case, such later date (not being later than 31st December 2005) as the Commission may agree pursuant to a request under Article 8(1) of the Directive, in respect of all discharges from agglomerations with a population equivalent of more than 15,000;

b

by 31st December 2005 in respect of all discharges from agglomerations with a population equivalent of between 10,000 and 15,000;

c

by 31st December 2005 in respect of all discharges to freshwaters and estuaries from agglomerations with a population equivalent of between 2,000 and 10,000.

2

Subject to paragraph (3) below, treatment plants which provide more stringent treatment than that described in paragraph (1) above shall be provided by 31st December 1998 in respect of all discharges from agglomerations with a population equivalent of more than 10,000 into sensitive areas, or into the relevant catchment areas of sensitive areas where the discharges contribute to the pollution of these areas.

3

Paragraph (2) above shall not apply in relation to a sensitive area where the Authority has certified that it is satisfied, as a result of monitoring, that the minimum percentage of reduction of the overall load entering all urban waste water treatment plants in that area, and all urban waste water treatment plants in the catchment area of that area the discharges from which contribute to the pollution of that area, is at least 75% for total phosphorus and at least 75% for total nitrogen.

4

Where, following a review of the identification of waters as sensitive areas or high natural dispersion areas under regulation 3, an area ceases to be identified as a high natural dispersion area or becomes identified as a sensitive area, then, as respects that area, paragraph (1) or, as the case may be, paragraph (2) above shall have effect as if the relevant date specified in that paragraph were the seventh anniversary of the change of identification or, if later, the date so specified.

5

Discharges of urban waste water from agglomerations with a population equivalent of between 10,000 and 150,000 (or, in an exceptional case and with the agreement of the Commission pursuant to Article 8(5) of the Directive, of more than 150,000) to coastal waters which are in high natural dispersion areas, and discharges from agglomerations with a population equivalent of between 2,000 and 10,000 into estuaries which are in high natural dispersion areas, may be subjected to less stringent treatment than that described in paragraph (1) above so long as—

a

the discharges receive at least primary treatment in conformity with the control procedures set out in Part II of Schedule 3; and

b

the Authority has certified that it is satisfied that comprehensive studies have indicated that such discharges will not adversely affect the environment.

6

The Authority shall provide the Secretary of State with such information concerning the studies mentioned in paragraph (5)(b) above as he may require for the purpose of enabling him to comply with Article 6(2) of the Directive.

7

Appropriate treatment of urban waste water entering collecting systems shall be provided by 31st December 2005 in respect of—

a

discharges to freshwaters and estuaries from agglomerations with a population equivalent of less than 2,000; and

b

discharges to coastal waters from agglomerations with a population equivalent of less than 10,000.

8

In this regulation—

a

“appropriate treatment” means treatment of urban waste water by any process and/or disposal system which after discharge allows the receiving waters to meet the relevant quality objectives and the relevant provisions of the Directive and other Community Directives;

b

“primary treatment” means treatment of urban waste water by a physical and/or chemical process involving settlement of suspended solids, or other processes in which the BOD5 of the incoming waste water is reduced by at least 20% before discharge and the total suspended solids of the incoming waste water are reduced by at least 50%.

Discharges of treated urban waste water6

1

Discharges from urban waste water treatment plants described in paragraph (1) or (2) of regulation 5, or from any such plant which provides treatment in accordance with paragraph (5) of that regulation, (including any such plants which are provided other than by sewerage undertakers) shall satisfy the relevant requirements of Part I of Schedule 3.

2

It shall be the duty of the Authority, in exercising its functions under Chapter II of Part III of the Water Resources Act 1991 M3 (pollution offences), to secure—

a

with respect to any such discharge as is described in paragraph (1) above, that the requirements of that paragraph are satisfied;

b

with respect to any discharge described in paragraph (5) or (7) of regulation 5 (including any such discharge from an urban waste water treatment plant which is provided other than by a sewerage undertaker), that the requirements of the said paragraph (5) or, as the case may be, the said paragraph (7) are satisfied;

c

with respect to any discharge from a collecting system described in regulation 4 or an urban waste water treatment plant described in regulation 5, the limitation of pollution of receiving waters due to storm water overflows;

d

with respect to the discharge of sludge—

i

that the discharge of sludge to surface waters is phased out by 31st December 1998; and

ii

that the total amount of toxic, persistent or bioaccumulable materials in the sludge which may be discharged to surface waters pursuant to consents under the said Chapter II is controlled by such consents and progressively reduced during the period ending on that date.

3

The Authority shall at regular intervals review and, if necessary for the purpose of complying with this regulation, modify or revoke consents granted under the said Chapter II.

4

Nothing in paragraph 7 of Schedule 10 to the Water Resources Act 1991 shall restrict the power of the Authority to modify or revoke a consent in pursuance of the duty imposed by this regulation.

5

All lakes and ponds shall be treated as controlled waters for the purposes of section 85 of that Act (offences of polluting controlled waters) insofar as that section relates to the discharge of waste water from urban waste water treatment plants.

Discharges of industrial waste water to collecting systems or treatment plants7

1

It shall be the duty of each of the following, that is to say—

a

every sewerage undertaker;

b

the F4Water Services Regulation Authority; and

c

the Secretary of State,

in exercising their functions under Chapter III of Part IV of the Water Industry Act 1991 (trade effluent) with respect to any discharge of industrial waste water, to secure that the requirements of Schedule 4 are met in respect of that discharge.

2

Nothing in subsection (1) or (2) of section 121 of that Act (conditions of consent) shall be construed as restricting the power of a sewerage undertaker to impose in any consent under the said Chapter III such conditions as are necessary to comply with paragraph (1) above.

3

Nothing in any agreement entered into between a sewerage undertaker or its predecessor and the owner or occupier of premises used for carrying on any trade or industry shall be treated as a consent or authorisation for the purposes of the said Chapter III unless the terms of that agreement are such as will secure that the requirements of Schedule 4 are met in respect of any discharge to which the agreement relates.

4

Sewerage undertakers shall review, and if necessary modify, the consents or authorisations granted or deemed to be granted under the said Chapter III at regular intervals.

5

For the purposes of complying with paragraph (1) above, a sewerage undertaker may vary any agreement under section 129 of the Water Industry Act 1991 which provides for the discharge of industrial waste water to an urban waste water treatment plant without first entering a public sewer, and any such agreement shall not be enforceable if and to the extent that it permits any discharge of industrial waste water in respect of which the requirements of Schedule 4 are not met.

6

Nothing in the said Chapter III shall—

a

restrict the power of a sewerage undertaker or the Secretary of State to vary a consent or authorisation in pursuance of the duty imposed by this regulation; or

b

render a sewerage undertaker or the Secretary of State liable to pay compensation as a consequence of any such variation made in pursuance of that duty.

7

The duty imposed on sewerage undertakers by this regulation shall be enforceable under section 18 of the Water Industry Act 1991 by the F4Water Services Regulation Authority.

Discharges of certain industrial waste water into receiving waters8

1

This regulation applies to discharges of biodegradable industrial waste water from plants representing 4,000 p.e. or more belonging to the industrial sectors listed in Schedule 5 which does not enter urban waste water treatment plants before discharge to receiving waters.

2

It shall be the duty of the Authority to impose, in every consent granted under Chapter II of Part III of the Water Resources Act 1991 (pollution offences) with respect to any discharge on or after 31st December 2000 to which this regulation applies (whether on the grant of consent or by notice under paragraph 6(2) of Schedule 10 to that Act), conditions which are appropriate to the nature of the industry concerned for the discharge of such waste water, and nothing in paragraph 7 of Schedule 10 to that Act shall restrict the power of the Authority to modify a consent in pursuance of the duty imposed by this paragraph.

3

It shall be the duty of the Authority, in exercising its functions under section 28(3) and (4) of the Environmental Protection Act 1990 M4 (authorisations under Part I of that Act and other statutory controls) (with respect to any process giving rise to a discharge to which this regulation applies, to secure that any authorisation granted in respect of that process includes conditions in respect of the discharge of such waste water on or after 31st December 2000 which are appropriate to the nature of the industry concerned.

4

All lakes and ponds shall be treated as controlled waters for the purposes of the enactments mentioned in paragraphs (2) and (3) above insofar as they relate to discharges to which this regulation applies.

Dumping of sludge from ships9

It shall be the duty of the licensing authority (within the meaning of section 24 of the Food and Environment Protection Act 1985 M5), in the exercise of its functions under Part II of that Act (deposits in the sea), to secure that—

a

the dumping of sludge from ships to surface waters is phased out by 31st December 1998; and

b

the total amount of toxic, persistent or bioaccumulable materials in sludge so disposed of is licensed for disposal and progressively reduced in the period ending on that date.

Samples and records10

1

In this regulation—

a

a “relevant condition” means a condition imposed for the purposes of regulation 6(2) in a consent under Chapter II of Part III of the Water Resources Act 1991;

b

“the operator” means, in relation to a relevant condition, the person who operates the urban waste water treatment plant, discharges from which are authorised by the consent in which that condition is imposed.

2

Where the operator is required by a relevant condition to provide any apparatus for the purpose of measuring or recording the volume, rate of flow, nature, composition or temperature of any waste water, or for the purpose of collecting samples of waste water, any such apparatus so provided shall be presumed to register accurately unless the contrary is shown.

3

Any record—

a

produced by any such apparatus as is mentioned in paragraph (2) above; or

b

made by or on behalf of the operator in order to comply with a relevant condition,

shall be evidence of the matters appearing from the record and shall, in any proceedings under Chapter II of Part III of the Water Resources Act 1991, be admissible in evidence against the operator.

4

Where—

a

an entry is required by a relevant condition to be made in any record as to the observance of that or any other relevant condition; and

b

the entry has not been made,

that fact shall be admissible as evidence that that condition or, as the case may be, that other condition has not been observed.

5

Where, in compliance with a relevant condition, a sample of waste water is collected by apparatus installed for the purpose of collecting such samples automatically, the sample shall be treated, for the purpose of section 209 of the Water Resources Act 1991 (evidence of samples and abstractions), as being taken only at the time when it is removed from that apparatus.

6

For the purposes of the said section 209, a sample of waste water which is taken and analysed by the operator in compliance with a relevant condition shall not be treated as being taken on behalf of the Authority.

Monitoring11

1

It shall be the duty of the Authority—

a

to monitor or procure the monitoring by a competent authority or appropriate body of discharges from urban waste water treatment plants to verify compliance with the relevant requirements of Part I of Schedule 3 in accordance with the control procedures set out in Part II of that Schedule;

b

to monitor or procure the monitoring by a competent authority or appropriate body of amounts and composition of sludges disposed of to surface waters (other than by means of dumping from ships);

c

to monitor or procure the monitoring by a competent authority or appropriate body of waters subject to discharges from urban waste water treatment plants provided in accordance with regulation 5 in cases where it can be expected that the receiving environment will be significantly affected;

d

to carry out or procure the carrying out by a competent authority or appropriate body of monitoring and any other relevant studies to verify that discharges to which regulation 5(5) applies and the disposal of sludge to surface waters (other than by means of dumping from ships) do not adversely affect the environment.

2

It shall be the duty of the licensing authority (within the meaning of section 24 of the Food and Environment Protection Act 1985)—

a

to monitor or procure the monitoring by a competent authority or appropriate body of amounts and composition of sludges disposed of to surface waters by means of dumping from ships;

b

to carry out or procure the carrying out by a competent authority or appropriate body of monitoring and any other relevant studies to verify that the disposal of sludge to surface waters by means of dumping from ships does not adversely affect the environment.

3

The Authority and the licensing authority shall retain any information collected by them or by a competent authority or appropriate body in complying with paragraph (1) or (2) above and shall make it available to the Secretary of State on request.

Deposit of maps and certificates12

The Authority shall keep available at its principal office and at each of its principal regional offices, at all reasonable times, for inspection by the public free of charge—

a

the maps referred to in the definition of “estuary” in regulation 2(1);

F3b

. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

c

particulars of certificates issued under regulation 4(3), 5(3) and 5(5)(b).

Information and assistance required in connection with the control of pollution13

For the purposes of section 202 of the Water Resources Act 1991 (information and assistance required in connection with the control of pollution), the following obligations shall be treated as functions of the Secretary of State under the water pollution provisions of that Act:

a

the obligation under Article 16 of the Directive to publish every two years a situation report on the disposal of urban waste water and sludge in England and Wales;

b

the obligation under Article 17 of the Directive to establish, update and provide the Commission with information on a programme for the implementation of the Directive.

Signed by authority of the Secretary of State

Robert AtkinsMinister of State,Department of the Environment
John RedwoodSecretary of State for Wales