Notification of project

7.—(1) The planning supervisor shall ensure that notice of the project in respect of which he is appointed is given to the Executive in accordance with paragraphs (2) to (4) unless the planning supervisor has reasonable grounds for believing that the project is not notifiable.

(2) Any notice required by paragraph (1) shall be given in writing or in such other manner as the Executive may from time to time approve in writing and shall contain the particulars specified in paragraph (3) or, where applicable, paragraph (4) and shall be given at the times specified in those paragraphs.

(3) Notice containing such of the particulars specified in Schedule 1 as are known or can reasonably be ascertained shall be given as soon as is practicable after the appointment of the planning supervisor.

(4) Where any particulars specified in Schedule 1 have not been notified under paragraph (3), notice of such particulars shall be given as soon as is practicable after the appointment of the principal contractor and, in any event, before the start of construction work.

(5) Where a project is carried out for a domestic client then, except where regulation 5 applies, every contractor shall ensure that notice of the project is given to the Executive in accordance with paragraph (6) unless the contractor has reasonable grounds for believing that the project is not notifiable.

(6) Any notice required by paragraph (5) shall—

(a)be in writing or such other manner as the Executive may from time to time approve in writing;

(b)contain such of the particulars specified in Schedule 1 as are relevant to the project; and

(c)be given before the contractor or any person at work under his control starts to carry out construction work.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources