6.—(1) During the construction of the works the Council may take from the said Loch Assapol such water as they may require for such construction.
(2) After completion of the works the Council–
(a)shall not in any one day take from Loch Assapol a quantity of water greater than 785 cubic metres as measured through or over an approved gauge (Work No.2); and
(b)shall discharge into the Bunessan River from Loch Assapol in a uniform and continuous flow compensation water at a rate of not less than 2600 cubic metres per day as measured through or over an approved gauge (Work No.5).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.