Development is not permitted by Class G if—
(a)in the case of any Class G(a) development—
(i)it would consist of or include the installation or replacement of an electric line to which section 37(1) of the Electricity Act 1989(1) (consent required for overhead lines) applies; or
(ii)it would consist of or include the installation or replacement at or above ground level or under a highway used by vehicular traffic, of a chamber for housing apparatus and the chamber would exceed 29 cubic metres in capacity;
(b)in the case of any Class G(b) development—
(i)the development would take place in a National Park, an area of outstanding natural beauty, or a site of special scientific interest;
(ii)the height of any support would exceed 15 metres; or
(iii)the telecommunications line would exceed 1,000 metres in length;
(c)in the case of any Class G(d) development—
(i)the height of the original building would be exceeded;
(ii)the cubic content of the original building would be exceeded by more than 25% or, in the case of any building on article 1(5) land, by more than 10%, or
(iii)the floor space of the original building would be exceeded by more than 1,000 square metres or, in the case of any building on article 1(5) land, by more than 500 square metres;
(d)in the case of any Class G(e) development, the building would exceed 15 metres in height, or
(e)in the case of any Class G(f) development, it would consist of or include—
(i)the erection of a building, or the reconstruction or alteration of a building where its design or external appearance would be materially affected, or
(ii)the installation or erection by way of addition or replacement of any plant or machinery exceeding 15 metres in height or the height of any plant or machinery replaced, whichever is the greater.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: