Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
E.1(1) The prior approval of the mineral planning authority to development permitted by Class E is not required if—
(a)the external appearance of the mine or disused mine at or adjacent to which the development is to be carried out would not be materially affected;
(b)no building, plant or machinery, structure or erection—
(i)would exceed a height of 15 metres above ground level, or
(ii)where any building, plant, machinery, structure or erection is rearranged, replaced or repaired, would exceed a height of 15 metres above ground level or the height of what was rearranged, replaced or repaired, whichever is the greater,
and
(c)the development consists of the extension, alteration or replacement of an existing building, within the limits set out in paragraph (3).
(2) The approval referred to in Class E shall not be refused or granted subject to conditions unless the authority are satisfied that it is expedient to do so because—
(a)the proposed development would injure the amenity of the neighbourhood and modifications could reasonably be made or conditions reasonably imposed in order to avoid or reduce that injury, or
(b)the proposed development ought to be, and could reasonably be, sited elsewhere.
(3) The limits referred to in paragraph E.1(1)(c) are—
(a)that the cubic content of the building as extended, altered or replaced does not exceed that of the existing building by more than 25%, and
(b)that the floor space of the building as extended, altered or replaced does not exceed that of the existing building by more than 1,000 square metres.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.