Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
A. Development on any land during a period not exceeding 28 consecutive days consisting of–E+W
(a)the drilling of boreholes;
(b)the carrying out of seismic surveys; or
(c)the making of other excavations,
for the purpose of mineral exploration, and the provision or assembly on that land or adjoining land of any structure required in connection with any of those operations.
A.1 Development is not permitted by Class A if–
(a)it consists of the drilling of boreholes for petroleum exploration;
(b)any operation would be carried out within 50 metres of any part of an occupied residential building or a building occupied as a hospital or school;
(c)any operation would be carried out within a National Park, an area of outstanding natural beauty, a site of archaeological interest or a site of special scientific interest;
(d)any explosive charge of more than 1 kilogram would be used;
(e)any excavation referred to in paragraph A(c) would exceed 10 metres in depth or 12 square metres in surface area;
(f)in the case described in paragraph A(c) more than 10 excavations would, as a result, be made within any area of 1 hectare within the land during any period of 24 months; or
(g)any structure assembled or provided would exceed 12 metres in height, or, where the structure would be within 3 kilometres of the perimeter of an aerodrome, 3 metres in height.
A.2 Development is permitted by Class A subject to the following conditions–
(a)no operations shall be carried out between 6.00 p.m. and 7.00 a.m.;
(b)no trees on the land shall be removed, felled, lopped or topped and no other thing shall be done on the land likely to harm or damage any trees, unless the mineral planning authority have so agreed in writing;
(c)before any excavation (other than a borehole) is made, any topsoil and any subsoil shall be separately removed from the land to be excavated and stored separately from other excavated material and from each other;
(d)within a period of 28 days from the cessation of operations unless the mineral planning authority have agreed otherwise in writing–
(i)any structure permitted by Class A and any waste material arising from other development so permitted shall be removed from the land,
(ii)any borehole shall be adequately sealed,
(iii)any other excavation shall be filled with material from the site,
(iv)the surface of the land on which any operations have been carried out shall be levelled and any topsoil replaced as the uppermost layer, and
(v)the land shall, so far as is practicable, be restored to its condition before the development took place, including the carrying out of any necessary seeding and replanting.
B. Development on any land consisting of—E+W
(a)the drilling of boreholes;
(b)the carrying out of seismic surveys; or
(c)the making of other excavations,
for the purposes of mineral exploration, and the provision or assembly on that land or on adjoining land of any structure required in connection with any of those operations.
B.1 Development is not permitted by Class B if—
(a)it consists of the drilling of boreholes for petroleum exploration;
(b)the developer has not previously notified the mineral planning authority in writing of his intention to carry out the development (specifying the nature and location of the development);
(c)the relevant period has not elapsed;
(d)any explosive charge of more than 2 kilograms would be used;
(e)any excavation referred to in paragraph B(c) would exceed 10 metres in depth or 12 square metres in surface area; or
(f)any structure assembled or provided would exceed 12 metres in height.
B.2 Development is permitted by Class B subject to the following conditions—
(a)the development shall be carried out in accordance with the details in the notification referred to in paragraph B.1(b), unless the mineral planning authority have otherwise agreed in writing;
(b)no trees on the land shall be removed, felled, lopped or topped and no other thing shall be done on the land likely to harm or damage any trees, unless specified in detail in the notification refered to in paragraph B.1(b) or the mineral planning authority have otherwise agreed in writing;
(c)before any excavation other than a borehole is made, any topsoil and any subsoil shall be separately removed from the land to be excavated and stored separately from other excavated material and from each other;
(d)within a period of 28 days from operations ceasing, unless the mineral planning authority have agreed otherwise in writing—
(i)any structure permitted by Class B and any waste material arising from other development so permitted shall be removed from the land,
(ii)any borehole shall be adequately sealed,
(iii)any other excavation shall be filled with material from the site,
(iv)the surface of the land shall be levelled and any topsoil replaced as the uppermost layer, and
(v)the land shall, so far as is practicable, be restored to its condition before the development took place, including the carrying out of any necessary seeding and replanting,
and
(e)the development shall cease no later than a date six months after the elapse of the relevant period, unless the mineral planning authority have otherwise agreed in writing.
B.3 For the purposes of Class B—
“relevant period" means the period elapsing—
where a direction is not issued under article 7, 28 days after the notification referred to in paragraph B.1(b) or, if earlier, on the date on which the mineral planning authority notify the developer in writing that they will not issue such a direction, or
where a direction is issued under article 7, 28 days from the date on which notice of that decision is sent to the Secretary of State, or, if earlier, the date on which the mineral planning authority notify the developer that the Secretary of State has disallowed the direction.
C. For the purposes of Part 22—
“mineral exploration" means ascertaining the presence, extent or quality of any deposit of a mineral with a view to exploiting that mineral; and
“structure" includes a building, plant or machinery.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.