SCHEDULE 2E+W

PART 31E+WDEMOLITION OF BUILDINGS

Class AE+W

Permitted developmentE+W

A.  Any building operation consisting of the demolition of a building.

Development not permittedE+W

A.1  Development is not permitted by Class A where—

(a)the building has been rendered unsafe or otherwise uninhabitable by the action or inaction of any person having an interest in the land on which the building stands; and

(b)it is practicable to secure safety or health by works of repair or works for affording temporary support.

ConditionsE+W

A.2  Development is permitted by Class A subject to the following conditions—

(a)where demolition is urgently necessary in the interests of safety or health and the measures immediately necessary in such interests are the demolition of the building the developer shall, as soon as reasonably practicable, give the local planning authority a written justification of the demolition;

(b)where the demolition does not fall within sub-paragraph (a) and is not excluded demolition—

(i)the developer shall, before beginning the development, apply to the local planning authority for a determination as to whether the prior approval of the authority will be required to the method of demolition and any proposed restoration of the site;

(ii)the application shall be accompanied by a written description of the proposed development, a statement that a notice has been posted in accordance with sub-paragraph (iii) and any fee required to be paid;

(iii)subject to sub-paragraph (iv), the applicant shall display a site notice by site display on or near the land on which the building to be demolished is sited and shall leave the notice in place for not less than 21 days in the period of 28 days beginning with the date on which the application was submitted to the local planning authority;

(iv)where the site notice is, without any fault or intention of the applicant, removed, obscured or defaced before the period of 21 days referred to in sub-paragraph (iii) has elapsed, he shall be treated as having complied with the requirements of that sub-paragraph if he has taken reasonable steps for protection of the notice and, if need be, its replacement;

(v)the development shall not be begun before the occurrence of one of the following—

(aa)the receipt by the applicant from the local planning authority of a written notice of their determination that such prior approval is not required;

(bb)where the local planning authority give the applicant notice within 28 days following the date of receiving his application of their determination that such prior approval is required, the giving of such approval; or

(cc)the expiry of 28 days following the date on which the application was received by the local planning authority without the local planning authority making any determination as to whether such approval is required or notifying the applicant of their determination;

(vi)the development shall, except to the extent that the local planning authority otherwise agree in writing, be carried out—

(aa)where prior approval is required, in accordance with the details approved;

(bb)where prior approval is not required, in accordance with the details submitted with the application;

and

(vii)the development shall be carried out—

(aa)where approval has been given by the local planning authority, within a period of five years from the date on which approval was given;

(bb)in any other case, within a period of five years from the date on which the local planning authority were given the information referred to in sub-paragraph (ii).

Interpretation of Class AE+W

A.3  For the purposes of Class A—

Marginal Citations

M2Section 299A was inserted by section 12(3) of the Planning and Compensation Act 1991 (c. 34).

Class BE+W

Permitted developmentE+W

B.  Any building operation consisting of the demolition of the whole or any part of any gate, fence, wall or other means of enclosure.