4.  For Schedule 2 to the Principal Regulations there shall be substituted the following schedule—

Regulation 5(1)

SCHEDULE 2

Method of calculating amount of any payment in respect of levy

1.  In this Schedule:

  • the superscript " is used to denote the estimate made by the Director of the amount in question for the period in question to calculate the levy rate for that period or for part of it;

  • the superscript ' is used to denote the estimate made by the Director of the amount in question for the period in question to calculate the levy rate for the period of 12 months immediately following that period or for any part of that period of 12 months; and

  • the absence of a superscript is used to denote the actual amount in question.

2.  In this Schedule the following symbols have the following meanings–

  • Ay is the aggregate of the total costs calculated in relation to each public electricity supplier in accordance with Part I of Schedule 3 in respect of period y;

  • By is the aggregate of the total costs calculated in relation to each public electricity supplier in accordance with Part II of Schedule 3 in respect of period y;

  • Cy is the amount of the administrative expenses of the Director attributable to the levy incurred in respect of period y;

  • Ey is the aggregate amount of all interest payments pursuant to regulation 29(1) in respect of period y less the aggregate amount of all interest payments pursuant to regulation 29(2) in respect of period y;

  • Fy is the aggregate amount of all interest payments pursuant to regulation 30 received in period y;

  • Gy is the aggregate amount of levy or interest payments due in respect of period y which, in the opinion of the Director, will be either irrecoverable or recoverable only at excessive cost;

  • Xy is the aggregate amount (exclusive of levy and value added tax) charged (whether or not a bill or invoice has been delivered to a customer) by licensed suppliers for leviable electricity supplied by them in period y; and

  • Ky is the correction factor for y calculated in accordance with paragraph 5.

3.  Subject to any adjustment which may be required pursuant to the Regulations, the amount of any payment to be made by a licensed supplier in respect of the levy in period y shall be calculated by applying to the aggregate amount (exclusive of value added tax and levy) charged (whether or not any bill or invoice has been delivered to a customer) by the supplier for leviable electricity supplied by him during the qualifying month–

(a)except where sub-paragraph (b) of this paragraph applies, the percentage figure Ry where Ry is the percentage figure ry given by the formula–

after it has been rounded to the nearest tenth of a per centum (any odd twentieth of a per centum being rounded upwards); or

(b)in relation to a rate of levy to apply from the commencement of a qualifying month other than the first qualifying month of period y, the percentage figure R1y where R1y is the percentage figure r1y given by the formula–

after it has been rounded to the nearest tenth of a per centum (any odd twentieth of a per centum being rounded upwards) where–

  • L is the estimate made by the Director of the aggregate amount of levy payments due in respect of the qualifying months in period y preceding the qualifying month from the beginning of which R1y is to apply; and

  • M is the estimate made by the Director of the aggregate amount (exclusive of levy and value added tax) charged (whether or not a bill or invoice has been delivered to a customer) by licensed suppliers for leviable electricity supplied by them in those qualifying months.

4.  In the formulae in paragraph 3 the value of D"y is given by the formula–

.

5.  In the formulae in paragraph 3 the correction factor Ky shall be the amount of money, whether positive or negative, given by the following formula–

where–

  • D"y−1 has the value that was given by the Director to D"y on the last occasion on which he calculated the levy rate to apply in the period y−1;

  • Σn signifies the summation over all the qualifying months n=1 to 12 inclusive within the period y−1 or y−2 as the case may be;

  • Rn is the rate of levy that applied to month n in the period y−1 or y−2 as the case may be;

  • rn is whichever of the percentage figures ry or r1y was used in calculating the rate of levy that applied to month n in the period y−1;

  • Xn is the aggregate amount (exclusive of levy and value added tax) charged (whether or not a bill or invoice has been delivered to a customer) by licensed suppliers for leviable electricity supplied by them in month n in the period y−1 or y−2 as the case may be;

  • X"ny−1 has a value equal to such proportion of the value that was given by the Director to X"y on the last occasion on which he calculated the levy rate to apply in the period y−1 as in the opinion of the Director is attributable to month n in that period;

  • D"y−2 has the value that was given by the Director to D"y−1 on the last occasion on which he calculated the levy rate to apply in the period y−1;

  • X"ny−2 in respect of a month n in period y−2, has the value that was given by the Director to X"ny−1 in respect of that month on the last occasion on which he calculated the levy rate to apply in the period y−1;

  • Iy−1 is the arithmetic average of the LIBOR rates on the last day of each of the first six months in period y−1; and

  • Iy−2 is the arithmetic average of the LIBOR rates on the last day of each of the first six months in period y−2..

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources