Point in time view as at 01/07/1997. This version of this provision has been superseded.
You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Lifts Regulations 1997, Paragraph 3.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(3.1) The installer must lodge an application for assessment of his quality assurance system with a notified body of his choice. The application must include:
all relevant information for the lifts,
the documentation concerning the quality assurance system,
the technical documentation of the approved type and a copy of the EC type-examination certificate.
(3.2) The quality assurance system must ensure compliance of the lifts with the requirements of the Directive that apply to them.
All the elements, requirements and provisions adopted by the installer of a lift shall be documented in a systematic and orderly manner in the form of written policies, procedures and instructions. The quality assurance system documentation must permit a consistent interpretation of the quality programmes, plans, manuals and records.
It must contain in particular an adequate description of:
the quality objectives and the organizational structure, responsibilities and powers of the management with regard to the quality of the lifts,
the manufacturing, quality control and quality assurance techniques, processes and systematic actions that will be used,
the examinations and tests that will be carried out before, during and after installation(1),
the quality records, such as inspection reports and test data, calibration data, qualification reports of the personnel concerned, etc.,
the means to monitor the achievement of the required lift quality and the effective operation of the quality assurance system.
(3.3) The notified body must assess the quality assurance system to determine whether it satisfies the requirements referred to in Section 3.2. It presumes conformity with these requirements in respect of quality assurance systems that implement the relevant harmonized standard(2).
The auditing team must have at least one member with experience of assessment in the lift technology concerned. The assessment procedure must include an inspection visit to the installer’s premises.
The decision must be notified to the installer. The notification must contain the conclusions of the examination and the reasoned assessment decision.
(3.4) The installer must undertake to discharge the obligations arising from the quality assurance system as approved and to ensure that it is maintained in an appropriate and efficient manner.
The installer shall keep the notified body that has approved the quality assurance system informed of any intended updating of the quality assurance system.
The notified body must assess the modifications proposed and decide whether the modified quality assurance system will still satisfy the requirements referred to in Section 3.2 or whether a re-assessment is required.
It must notify its decision to the installer. The notification must contain the conclusions of the examination and the reasoned assessment decision.
These tests include at least the tests provided for in Annex VI, Section 4(b).
This harmonised standard will be EN 29002, supplemented where necessary to take account of the specific nature of the lifts.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.