Search Legislation

The Merchant Shipping (Passenger Ship Construction: Ships of Classes I, II and II(A)) Regulations 1998

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

More Resources

Changes to legislation:

There are currently no known outstanding effects for the The Merchant Shipping (Passenger Ship Construction: Ships of Classes I, II and II(A)) Regulations 1998, Section 62. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

GeneralU.K.

62.—(1) In every ship the machinery, boilers and other pressure vessels, associated piping systems and fittings shall be of a design and construction adequate for the service for which they are intended and shall be so installed and protected as to reduce to a minimum any danger to persons on board, due regard being paid to moving parts, hot surfaces and other hazards. The design shall have regard to the materials used in construction including design standards, material specifications, and certification etc, the purpose for which the equipment is intended, the working conditions to which it will be subjected and the environmental conditions on board.

(2) Where the arrangements of the main propulsion machinery are unconventional and without a known history of satisfactory service the Secretary of State may require a separate source of propulsion power to be provided sufficient to give the ship a navigable speed.

(3) The main and auxiliary machinery essential for the propulsion and overall safety of the ship shall be provided with effective means of control. In addition, suitable means shall be provided to ensure that machinery can be brought into operation from dead ship conditions.

(4) Where risk from over-speeding of machinery would otherwise exist, two independent means of control shall be provided to ensure that the safe speed is not exceeded; provided that where the Secreary of State considers it is safe to do so, a single means of limiting the speed of machinery may be permitted.

(5) All boilers, main or auxiliary machinery or any parts of such machinery, all steam, hydraulic, pneumatic and other systems and their associated fittings which are under internal pressure, shall be subjected to appropriate testing including a pressure test in excess of the working pressure, prior to being put into service for the first time. The pressure test shall have regard to—

[F1(a)the design and the materials of which the respective items are constructed;]

(b)the purpose for which they are intended to be used; and

(c)the working conditions under which they are intended to be used, and such parts shall be maintained in an efficient condition and be subject to periodic inspection/testing.

(6) Access shall be provided to facilitate the cleaning, maintain cleanliness, inspection and maintenance of main propulsion and auxiliary machinery including boilers and pressure vessels.

Additional requirements for ships constructed on or after 1st September 1984

(7) In every ship means shall be provided whereby the normal operation of propulsion machinery can be sustained or restored when there is a breakdown of—

(a)a generating set which serves as a main source of electrical power;

(b)the sources of steam supply;

(c)the boiler feed water systems;

(d)the fuel oil supply systems for boilers or engines;

(e)the sources of lubricating oil pressure;

(f)the sources of water pressure;

(g)a condensate pump and the arrangements to maintain vacuum in condensers;

(h)the mechanical air supply for boilers;

(i)an air compressor and receiver for starting or control purposes;

(j)the hydraulic, pneumatic or electrical means for control of main propulsion machinery including controllable pitch propellors; or

(k)any other auxiliary system essential for propulsion.

  • A partial reduction in propulsion capability from normal operation may be permitted if it can be shown that the safety of the ship will not be impaired.

(8) In any such ship the main propulsion machinery and all auxiliary machinery essential to the propulsion and the safety of the ship shall be designed to operate when the ship is upright and when inclined at any angle of list up to and including 15 degrees either way under static conditions and 22.5 degrees either way under dynamic conditions (rolling) and simultaneously inclined dynamically (pitching) 7.5 degrees by bow or stern. Where it can be shown that the overall safety of the ship will not be impaired, deviation from the aforesaid angles may be permitted, taking into account the type, size and service conditions.

Textual Amendments

Commencement Information

I1Reg. 62 in force at 12.11.1998, see reg. 1(1)

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.