- Latest available (Revised)
- Point in Time (07/10/2001)
- Original (As made)
Version Superseded: 02/12/2002
Point in time view as at 07/10/2001.
There are currently no known outstanding effects for the The Civil Procedure Rules 1998, PART 29.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Modifications etc. (not altering text)
C1Pt. 29 excluded (7.10.2001) by The Railway Administration Order Rules 2001 (S.I. 2001/3352), rules 1.1, 6.33(2)
Scope of this Part | Rule 29.1 |
Case management | Rule 29.2 |
Case management conference and pre-trial review | Rule 29.3 |
Steps taken by the parties | Rule 29.4 |
Variation of case management timetable | Rule 29.5 |
Listing questionnaire | Rule 29.6 |
Pre-trial review | Rule 29.7 |
Setting a trial timetable and fixing or confirming the trial date or week | Rule 29.8 |
Conduct of the trial | Rule 29.9 |
29.1 This Part contains general provisions about management of cases allocated to the multi-track and applies only to cases allocated to that track.
(Part 27 sets out the procedure for claims allocated to the small claims track)
(Part 28 sets out the procedure for claims allocated to the fast track)
29.2—(1) When it allocates a case to the multi-track, the court will—
(a)give directions for the management of the case and set a timetable for the steps to be taken between the giving of directions and the trial; or
(b)fix—
(i)a case management conference; or
(ii)a pre-trial review,
or both, and give such other directions relating to the management of the case as it sees fit.
(2) The court will fix the trial date or the period in which the trial is to take place as soon as practicable.
(3) When the court fixes the trial date or the trial period under paragraph (2), it will—
(a)give notice to the parties of the date or period; and
(b)specify the date by which the parties must file a listing questionnaire.
29.3—(1) The court may fix—
(a)a case management conference; or
(b)a pre-trial review,
at any time after the claim has been allocated.
(2) If a party has a legal representative, a representative—
(a)familiar with the case; and
(b)with sufficient authority to deal with any issues that are likely to arise, must attend case management conferences and pre-trial reviews.
(Rule 3.1(2)(c) provides that the court may require a party to attend the court)
29.4 If—
(a)the parties agree proposals for the management of the proceedings (including a proposed trial date or period in which the trial is to take place); and
(b)the court considers that the proposals are suitable,
it may approve them without a hearing and give directions in the terms proposed.
29.5—(1) A party must apply to the court if he wishes to vary the date which the court has fixed for—
(a)a case management conference;
(b)a pre-trial review;
(c)the return of a listing questionnaire under rule 29.6;
(d)the trial; or
(e)the trial period.
(2) Any date set by the court or these Rules for doing any act may not be varied by the parties if the variation would make it necessary to vary any of the dates mentioned in paragraph (1).
(Rule 2.11 allows the parties to vary a date by written agreement except where the rules provide otherwise or the court orders otherwise)
29.6—(1) The court will send the parties a listing questionnaire for completion and return by the date specified in directions given under rule 29.2(3) unless it considers that the claim can be listed for trial without the need for a listing questionnaire.
(2) Each party must file the completed listing questionnaire by the date specified by the court.
(3) If—
(a)a party fails to file the completed questionnaire by the date specified;
(b)a party has failed to give all the information requested by the listing questionnaire; or
(c)the court considers that a hearing is necessary to enable it to decide what directions to give in order to complete preparation of the case for trial,
the court may fix a date for a listing hearing or give such other directions as it thinks appropriate.
29.7 If, on receipt of the parties' listing questionnaires, the court decides—
(a)to hold a pre-trial review; or
(b)to cancel a pre-trial review which has already been fixed,
it will serve notice of its decision at least 7 days before the date fixed for the hearing or, as the case may be, the cancelled hearing.
29.8 As soon as practicable after—
(a)each party has filed a completed listing questionnaire;
(b)the court has held a listing hearing under rule 29.6(3); or
(c)the court has held a pre-trial review under rule 29.7,
the court will—
(i)set a timetable for the trial unless a timetable has already been fixed, or the court considers that it would be inappropriate to do so;
(ii)fix the date for the trial or the week within which the trial is to begin (or, if it has already done so, confirm that date); and
(iii)notify the parties of the trial timetable (where one is fixed under this rule) and the date or trial period.
29.9 Unless the trial judge otherwise directs, the trial will be conducted in accordance with any order previously made.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.