Module G (EC unit verification)

4.  The notified body must examine the design and construction of each item of pressure equipment and during manufacture perform appropriate tests as set out in the relevant standard(s) referred to in Article 5 of the Directive, or equivalent examinations and tests, to ensure its conformity with the requirements of the Directive which apply to it.

In particular the notified body must:

  • examine the technical documentation with respect to the design and the manufacturing procedures,

  • assess the materials used where these are not in conformity with the relevant harmonised standards or with a European approval for pressure equipment materials, and check the certificate issued by the material manufacturer in accordance with section 4.3 of Annex I,

  • approve the procedures for the permanent joining of parts or check that they have been previously approved in accordance with section 3.1.2 of Annex I,

  • verify the qualifications or approvals required under sections 3.1.2 and 3.1.3 of Annex I,

  • carry out the final inspection referred to in section 3.2.1 of Annex I, perform or have performed the proof test referred to in section 3.2.2 of Annex I, and examine the safety devices, if applicable.

4.1. The notified body must affix its identification number or have it affixed to the pressure equipment and draw up a certificate of conformity for the tests carried out. This certificate must be kept for a period of ten years.

4.2. The manufacturer, or his authorised representative established within the Community, must ensure that the declaration of conformity and certificate of conformity issued by the notified body can be made available on request.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources