24.—(1) The compulsory powers of acquisition and temporary possession conferred by this Order shall not be applicable to land owned by Railtrack PLC.
(2) Subject to the following provisions of this article, the powers under article 4 above shall not be exercisable where Work No. 2 traverses the land of Railtrack PLC numbered on the deposited plan 5 in Porthmadog and there crosses its Cambrian Coast railway except with the consent of Railtrack PLC.
(3) A consent given for the purposes of paragraph (2) above may be made subject:—
(a)to the requirement that the relevant authorised works or any part of those works affecting the property of Railtrack PLC shall be executed by Railtrack PLC; and
(b)to such reasonable conditions as may be specified by Railtrack PLC;
but shall not be unreasonably withheld.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: