The Welsh Highland Railway Order 1999

Article 16

SCHEDULE 6LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN OR USE MADE

(1)(2)(3)(4)
AreaNumber of land shown on deposited plansPurpose for which temporary possession may be takenAuthorised work
Llanwnda4Access to railway formation and bridge worksWork No. 1 (part)
5New access track to be constructed on landowner’s own landWork No. 1a
Betws Garmon4Access to railway formationWork No. 1 (part)
5Existing bridge to be rebuiltWork No. 1 (part)
6Existing bridge to be rebuiltWork No. 1 (part)
7Existing bridge to be rebuiltWork No. 1 (part)
8Existing bridge to be rebuiltWork No. 1 (part)
9Access for worksWork No. 1 (part)
10Existing accommodation over bridge to be rebuilt in altered positionWork No. 1d
11Existing accommodation over bridge to be rebuilt in altered positionWork No. 1d
13Existing bridge to be rebuiltWork No. 1 (part)
14Existing bridge to be rebuilt and access to highway usedWork No. 1 (part)
15Existing bridge to be rebuilt and new access track to be made on landowner’s own landWork No. 1c
16New access track to be made on landowner’s own landWork No. 1c
17Existing bridge to be rebuiltWork No. 1 (part)
18Existing bridge to be rebuiltWork No. 1 (part)
19New access track to be made on landowner’s own landWork No. 1e
20New access track to be made on landowner’s own landWork No. 1e
22Temporary work siteWork No. 1 (part)
23Existing bridge to be rebuiltWork No. 1 (part)
24Existing bridge to be rebuiltWork No. 1 (part)
25Existing bridge to be rebuiltWork No. 1 (part)
26Existing bridge to be rebuiltWork No. 1 (part)
29Access route and drainage worksWork No. 1 (part)
30Drainage worksWork No. 1 (part)
31For access and bridleway diversionWork No. 1 (part)
31AAccess for bridge to be repairedWork No. 1 (part)
31BAccess for bridge to be repairedWork No. 1 (part)
31CAccess for bridge to be repairedWork No. 1 (part)
31DAccess for bridge to be repairedWork No. 1 (part)
31EAccess for bridge to be repairedWork No. 1 (part)
32Public footpath to be divertedWork No. 1 (part)
Beddgelert2Public bridleway to be divertedWork No. 2 (part)
2AFor accessWork No. 2 (part)
2BFor footpath to be created between car park and station by easement over landowner’s own landWork No. 2 (part)
15Construction of access trackWork No. 2a
20Existing bridge to be rebuiltWork No. 2 (part)
21New access track to be created on landowner’s own landWork No. 2b
22Existing bridge to be rebuiltWork No. 2 (part)
Llanfrothen2Existing bridge to be rebuiltWork No. 2 (part)
3Existing bridge to be rebuiltWork No. 2 (part)
Dolbenmaen2Level crossing to be rebuiltLevel crossing No. 4
Porthmadog3Occupation and public bridleway crossing to be rebuiltWork No. 2 (part)
5Level crossing to be rebuiltWork No. 2 (part)
6Pottery entrance to be reformedWork No. 2 (part)
7For traffic signals to be installedLevel crossing No. 5
15For bridge worksWork No. 3 (part)
16For railway track, road reconstruction, traffic signals to be installed and for widening of the CobLevel crossing No. 6
17For railway track, road reconstruction and traffic signals to be installedLevel crossing No. 6
18Station improvements on own landWork No. 3 (part)
19For widening of the CobWork No. 3 (part)