PART IIWORKS

Streets

Permanent stopping up of street

8.—(1) Subject to the provisions of this article, Railtrack may, in connection with the construction of the authorised works, permanently stop up the street specified in columns (1) and (2) of Schedule 3 to this Order to the extent specified in column (3) of that Schedule.

(2) The new street to be substituted for the street to be stopped up under this article, and which is specified in column (4) of that Schedule, shall be completed to the reasonable satisfaction of the street authority and open for public use within three months after all bridge girders have been replaced in connection with Work No. 3.

(3) Any person who suffers loss by the extinguishment of any private right of way under this article shall be entitled to compensation to be determined, in case of dispute, under Part I of the 1961 Act.

(4) This article is subject to paragraph 2 of Schedule 6 to this Order.