Safeguarding works to buildings
13.—(1) Subject to the following provisions of this article, the undertaker may at its own expense and from time to time carry out such safeguarding works to any building lying within the relevant distance of any authorised works (other than works under this article), as the undertaker considers to be necessary or expedient.
(2) Safeguarding works may be carried out—
(a)at any time before or during the construction in the vicinity of the building of any part of the authorised works; or
(b)after the completion of the construction of that part of the authorised works, at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised works is first opened for use.
(3) For the purpose of determining how the functions under this article are to be exercised the undertaker may enter and survey any building falling within paragraph (1) above and any land belonging to it.
(4) For the purpose of carrying out safeguarding works under this article to a building the undertaker may (subject to paragraphs (5) and (6) below)—
(a)enter the building and any land belonging to it; and
(b)where the works cannot be carried out reasonably conveniently without entering land adjacent to the building, enter the adjacent land (but not any building erected on it).
(5) Before exercising a right—
(a)under paragraph (1) above to carry out safeguarding works to a building,
(b)under paragraph (3) above to enter a building,
(c)under paragraph (4)(a) above to enter a building or land, or
(d)under paragraph (4)(b) above to enter land,
the undertaker shall, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days' notice of its intention to exercise the right and, in a case falling within sub-paragraph (a) or (c) above, specifying the safeguarding works proposed to be carried out.
(6) Where notice is served under paragraph (5)(a), (c) or (d) above, the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question whether it is necessary or expedient to carry out the safeguarding works or to enter the building or land to be referred to arbitration under article 36 below.
(7) The undertaker shall compensate the owners and occupiers of any building or land in relation to which the powers of this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.
(8) Where—
(a)safeguarding works are carried out under this article to a building, and
(b)within the period of 5 years beginning with the day on which the part of the authorised works constructed within the vicinity of the building is first opened for use it appears that the safeguarding works are inadequate to protect the building against damage caused by the construction or operation of that part of the works,
the undertaker shall compensate the owners and occupiers for any damage sustained by them.
(9) Subject to article 35 of this Order, nothing in this article shall relieve the undertaker from any liability to pay compensation under section 10(2) of the 1965 Act.
(10) Any compensation payable under paragraph (7) or (8) shall be determined, in case of dispute, under Part I of the Land Compensation Act 1961(1).
(11) In this article—
(a)any reference to a building within a relevant distance of a work includes—
(i)in the case of a work under the surface of the ground, a reference to any building within the relevant distance of the point on the surface below which the work is situated; and
(ii)where a work has not commenced, a reference to any building within the relevant distance of the proposed site of the work;
(b)“safeguarding works”, in relation to a building means—
(i)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, maintenance or operation of the authorised works; and
(ii)any works the purpose of which is to remedy any damage which has been caused to the building by the construction, maintenance or operation of the authorised works; and
(c)“relevant distance”, in relation to any work, means:
(i)in the case of works under the surface of the ground, within the limit line shown marked “50 metres from new construction” on the deposited plan entitled “Works Plan”; and
(ii)in any other case, within the limit line shown marked “35 metres from new construction” on the deposited plan entitled “Works Plan”.