Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
17.—(1) Subject to paragraphs (3) and (6) below, where–
(a)any activity in relation to a relevant project is being, or has been, carried out without the necessary consent or approval of the [F1OGA] granted in accordance with these Regulations or otherwise than in accordance with a relevant requirement imposed in accordance with these Regulations; or
(b)a relevant project is being, or has been, carried out in breach of any condition attached to any consent or approval, being a condition so attached for the purpose of reducing or eliminating any significant adverse effects on the environment,
the court may, on the application of the Secretary of State, make an order restraining the continued carrying out of the relevant project or compelling the performance of any act required to be done by a condition of the kind mentioned in sub-paragraph (b) above.
(2) The court may, in addition to making such an order as is mentioned in paragraph (1) above, make an order requiring–
(a)the removal, so far as is practicable in all the circumstances, of any structure erected—
(i)without the consent or approval of the [F2OGA] as mentioned in paragraph (1)(a) above;
(ii)otherwise than in accordance with any relevant requirement as mentioned in paragraph (1)(a) above; or
(iii)in breach of a condition of the kind mentioned in paragraph (1)(b) above; and
(b)where it orders the removal of any structure, the reinstatement of the site where the structure was erected.
(3) The court shall not grant an order under this regulation in respect of a breach of any condition of the kind mentioned in paragraph (1)(b) above where–
(a)the breach in question was due to circumstances beyond the control of the undertaker and the breach could not reasonably have been prevented by the undertaker; or
(b)the breach occurred as a result of anything required to be done as a matter of urgency for the purposes of securing the safety of any person.
(4) Where the undertaker fails to comply with the terms of an order made pursuant to paragraph (2) above within such time as may be specified in it or, in default of such specification, within a reasonable time of the making of the order, the Secretary of State may himself take the action required to be taken by the order and the reasonable costs and expenses of doing so shall be recoverable as a debt from the undertaker.
(5) Where the Secretary of State takes action in accordance with paragraph (4) above, that action shall be without prejudice to any consequences which may flow from the undertaker’s failure to comply with the order.
(6) This regulation shall not apply to anything done in relation to a project which is the subject of an exemption granted pursuant to regulation 13 above (exempt projects).
Textual Amendments
F1Word in reg. 17(1)(a) substituted (1.10.2016) by The Energy (Transfer of Functions, Consequential Amendments and Revocation) Regulations 2016 (S.I. 2016/912), regs. 1(1), 7(10)(a)
F2Word in reg. 17(2)(a)(i) substituted (1.10.2016) by The Energy (Transfer of Functions, Consequential Amendments and Revocation) Regulations 2016 (S.I. 2016/912), regs. 1(1), 7(10)(b)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: