You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.
Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.
There are currently no known outstanding effects for the The Pollution Prevention and Control (England and Wales) Regulations 2000, Section 21.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
21.—(1) The regulator may at any time revoke a permit, in whole or in part, by serving a notice (“a revocation notice”) on the operator.
(2) Without prejudice to the generality of paragraph (1), the regulator may serve a notice under this regulation in relation to a permit where—
(a)the permit authorises the carrying out of a specified waste management activity and it appears to the regulator that the operator of the installation or mobile plant concerned has ceased to be a fit and proper person to carry out that activity by reason of his having been convicted of a relevant offence within the meaning of regulation 4(5)(a) or by reason of the management of that activity having ceased to be in the hands of a technically competent person;
(b)the holder of the permit has ceased to be the operator of the installation or mobile plant covered by the permit.
(3) A revocation notice may—
(a)revoke a permit entirely;
(b)revoke a permit only in so far as it authorises the operation of some of the installations or mobile plant to which it applies;
(c)revoke a permit only in so far as it authorises the carrying out of some of the activities which may be carried out in an installation or by means of mobile plant to which it applies.
(4) A revocation notice shall specify—
(a)in the case of a revocation mentioned in sub-paragraph (b) or (c) of paragraph (3) (a “partial revocation”), the extent to which the permit is being revoked;
(b)in all cases, the date on which the revocation shall take effect, which shall be at least 28 days after the date on which the notice is served.
(5) If, in the case of a revocation mentioned in sub-paragraph (a) or (b) of paragraph (3) applying to a Part A installation or Part A mobile plant, the regulator considers that it is appropriate to require the operator to take steps, once the installation or mobile plant is no longer in operation, to—
(a)avoid any pollution risk resulting from the operation of the installation or mobile plant on the site or, in the case of a partial revocation, that part of the site used for the operation of that installation or mobile plant, or
(b)return the site, or that part of the site, to a satisfactory state,
the revocation notice shall specify that this is the case and, in so far as those steps are not already required to be taken by the conditions of the permit, the steps to be taken.
(6) Subject to paragraph (7) and regulation 27(6), a permit shall cease to have effect, or, in the case of a partial revocation, shall cease to have effect to the extent specified in the revocation notice, from the date specified in the notice.
(7) Where paragraph (5) applies the permit shall cease to have effect to authorise the operation of the Part A installation or Part A mobile plant from the date specified in the revocation notice but shall continue to have effect in so far as the permit requires steps to be taken once it is no longer in operation until the regulator issues a certificate stating that it is satisfied that all such steps have been taken.
(8) Where a permit continues to have effect as mentioned in paragraph (7), any steps specified in a revocation notice pursuant to paragraph (5) shall be treated as if they were required to be taken by a condition of the permit and regulations 17, 23, 24, and 32(1)(b) shall apply in relation to the requirement to take such steps, and to any other conditions in the permit which require steps to be taken once the installation is no longer in operation, until the regulator issues a certificate as mentioned in paragraph (7).
(9) A regulator which has served a revocation notice may, before the date on which the revocation takes effect, withdraw the notice.
(10) Regulation 19(11) shall apply for the purpose of deciding whether a pollution risk results from the operation of a Part A installation or Part A mobile plant for the purpose of this regulation as it applies for the purpose of regulation 19.
Commencement Information
I1Reg. 21 in force at 1.8.2000, see reg. 1(1)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: