PART IIWORKS PROVISIONS
Principal powers
Power to deviate4
In constructing or maintaining any of the scheduled works, the Council may—
a
deviate laterally from the lines or situations shown on the deposited plans within the limits of deviation relating to that work shown on those plans; and
b
deviate vertically from the levels shown on the deposited sections—
i
to any extent not exceeding 3 metres upwards; and
ii
to any extent downwards.