The Leeds Supertram (Land Acquisition and Road Works) Order 2001

Further works

13.—(1) The Executive may, in the lines and situations shown on the works plans and in accordance with the levels shown on the sections, construct and maintain the following works—

  • Work No. 1: a road for the realignment of Chadwick Street in the City, commencing in Chadwick Street at a point 20 metres east of its junction with Black Bull Street and terminating at a point 121 metres south-east of its commencement; and

  • Work No. 2: a road for the realignment of Waterloo Street in the City, commencing in Waterloo Street at a point 20 metres east of its junction with Hunslet Road and terminating at a point 109 metres east of its commencement.

(2) In constructing and maintaining the road works, the Executive may—

(a)deviate laterally from the line and situation shown on the works plans within the limits of deviation for that work shown on the works plans;

(b)deviate vertically from the levels shown on the sections to any extent not exceeding 3 metres upwards or downwards.

(3) The Executive may carry out and maintain such of the following works as may be necessary or expedient for the purposes of, in connection with or in consequence of, the construction of the road works, namely—

(a)works for the alteration or demolition of any building or structure,

(b)works to alter the position of apparatus or street furniture, including mains, sewers, drains and cables,

(c)landscaping and other works to mitigate any adverse effects of the construction, maintenance or operation of the road works, and

(d)works for the benefit or protection of premises affected by the road works,

together with such other works (of whatever nature) as may be necessary or expedient as aforementioned.

(4) Works carried out under paragraph (3) above shall be carried out within the limits of land to be acquired.