The information referred to in regulation 9(2) is as follows—
(a)the names or positions of persons authorised to set emergency procedures in motion and of persons authorised to take charge of and co-ordinate the off-site mitigatory action;
(b)the arrangements for receiving early warning of incidents, and alert and call-out procedures;
(c)the arrangements for co-ordinating resources necessary to implement the off-site emergency plan;
(d)the arrangements for providing assistance with on-site mitigatory action;
(e)the arrangements for off-site mitigatory action;
(f)the arrangements for providing the public with specific information relating to the emergency and the behaviour which it should adopt; and
(g)the arrangements for emergency exposures including the dose levels which have been determined as appropriate for the purposes of putting into effect the emergency plan.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: