PART 3MANAGEMENT ACTIVITIES

Column 1

Column 2

Activity

Maximum rate in £ per hectare of land per annum (except where otherwise stated)

1.

Maintenance of cultivated land.

18

2.

Management of enclosed permanent grassland.

50

3.

Management of enclosed permanent rough grazing.

46

4.

Enhanced management of pasture.

110

5.

Enhanced management of meadowland.

170

6.

Regeneration to create extensive pasture.

160

7.

Regeneration to create extensive meadowland.

170

8.

Where management of any kind under item 1, 2, 3, 4 or 6 is undertaken, additional management so as to create wet areas.

90

9.

In relation to moorland—

(a) maintenance of moorland

32

(b) enhanced management of moorland

62

(c) regeneration of moorland through temporary stock exclusion.

30

10.

Management of woodland to enhance its nature conservation and landscape value.

120

11.

The provision of public access routes.

170

12.

In relation to walls—

(a) restoration

£20 per metre

(b) top wiring supplement.

£1 per metre