PART III ACQUISITION AND POSSESSION OF LAND
SCHEDULES
MODIFICATION OF COMPENSATION AND COMPULSORY PURCHASE ENACTMENTS FOR CREATION OF NEW RIGHTS
3.(1) The 1965 Act shall have effect with the modifications...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
FOR PROTECTION OF RAILWAY UNDERTAKERS
1.(1) The following provisions of this Part of this Schedule...
2.(1) DLRL shall not exercise the powers conferred by article...
3.(1) DLRL shall before commencing construction of any specified work...
4.(1) Any specified work shall, when commenced, be constructed—
5.DLRL shall— (a) at all times afford reasonable facilities to...
6.Railtrack PLC shall at all times afford reasonable facilities to...
7.(1) If any alterations or additions, either permanent or temporary,...
8.DLRL shall repay to Railtrack PLC all reasonable fees, costs,...
9.(1) In this paragraph— “EMI” means, subject to sub-paragraph (2)...
11.DLRL shall not provide any illumination or illuminated sign or...
12.Any additional expenses which Railtrack may reasonably incur in altering,...
13.(1) DLRL shall pay to Railtrack PLC all reasonable costs,...
14.In the assessment of any sums payable to Railtrack under...
PART II THE UNDERGROUND COMPANIES
16.(1) The following provisions of this Part of this Schedule...
17.(1) DLRL shall not exercise the powers conferred by article...
18.(1) DLRL shall before commencing construction of any specified work...
19.(1) Any specified work and any protective work specified pursuant...
20.DLRL shall— (a) at all times afford reasonable facilities to...
21.The Underground companies shall at all times afford reasonable facilities...
22.(1) If any alterations or additions, either permanent or temporary,...
23.DLRL shall repay to LUL all reasonable fees, costs, charges...
26.(1) DLRL shall pay to LUL all reasonable costs, charges,...
27.In the assessment of any sums payable to the Underground...
28.DLRL and the Underground companies may enter into, and carry...
FOR PROTECTION OF THE LONDON BOROUGH OF NEWHAM
1.(1) The following provisions of this Schedule shall, unless otherwise...
2.Before commencing to construct any scheduled work DLRL shall consult...
4.Before commencing to construct any authorised work which will involve...
6.DLRL shall not, except with the consent of the Council,...
7.Except in an emergency or where reasonably necessary to secure...
8.DLRL shall, if reasonably so required by the Council, provide...
9.DLRL shall indemnify the Council against any claim which may...
10.Wherever in this Schedule provision is made with respect to...
11.Unless otherwise agreed between the parties any difference arising between...
FOR PROTECTION OF THE ENVIRONMENT AGENCY
1.The following provisions of this Schedule shall, unless otherwise agreed...
2.Before applying for any consent under section 109 of the...
3.In carrying out any works under the powers conferred by...
7.DLRL may relocate the turning bay on the Barrier Access...
10.The approval of plans supplied under paragraph 9 above shall...
11.For the purposes of paragraph 9 above, “banks” has the...
12.Any culvert or any structure designed to contain or divert...
13.Nothing in paragraph 12 above shall have the effect of...
14.If any operation or work is carried out in contravention...
FOR PROTECTION OF SPECIFIED UNDERTAKERS
Removal of apparatus and construction of alternative apparatus by DLRL
Retained apparatus: protection and plan approval
20.Not less than 56 days before commencing to construct or...
22.DLRL shall not commence the construction or renewal of any...
23.Any approval of the specified undertaker required under paragraph 22...
25.A specified work shall be constructed (and in the case...
27.Nothing in paragraphs 20 or 26 above shall preclude DLRL...
28.DLRL shall not be required to comply with paragraph 20...
29.Nothing in paragraph 28 above shall entitle DLRL to carry...