- Latest available (Revised)
- Original (As made)
This is the original version (as it was originally made). This item of legislation is currently only available in its original format.
17.—(1) At any time during the maintenance period relating to any of the scheduled works, the undertaker may—
(a)enter upon and take temporary possession of any land shown on the land plan for the purpose of, or in connection with, maintaining the work or any ancillary works connected with it,
(b)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
(2) Paragraph (1) shall not authorise the undertaker to take temporary possession of—
(a)any house or garden belonging to a house, or
(b)any building (other than a house) if it is not for the time being occupied.
(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker shall serve notice of the intended entry on the owners and occupiers of the land.
(4) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance works for which possession of the land was taken.
(5) Before giving up possession of the land of which temporary possession has been taken under this article, the undertaker shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
(6) The undertaker shall pay compensation to the owners and occupiers of the land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
(7) Any disputes as to a person’s entitlement to compensation under paragraph (6), or as to the amount of compensation, shall be determined under Part I of the Land Compensation Act 1961.
(8) Without prejudice to article 28, nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act, or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (6).
(9) Where the undertaker takes possession of land under this article, it shall not be required to acquire the land or any interest in it.
(10) In this article “the maintenance period”, in relation to a scheduled work, means the period of 5 years beginning with the date on which the scheduled works are opened for use.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: