PART 2WORKS PROVISIONS
Streets
Permanent and temporary stopping up and diversion of streets8.
(1)
Subject to the provisions of this article, the undertaker may, in connection with the construction of the authorised works, permanently stop up each of the streets specified in column (1) of Part 2 of Schedule 3 to this Order to the extent specified in column (2) of Part 2 of that Schedule.
(2)
Subject to the provisions of this article, the undertaker may, in connection with the construction of the authorised works, temporarily stop up each of the streets specified in column (1) of Part 3 of Schedule 3 to this Order to the extent specified in column (2) of Part 3 of that Schedule.
(3)
No street specified in column (1) of Parts 2 and 3 of Schedule 3 to this Order (being a street stopped up for which a substitute is to be provided) shall be wholly or partly stopped up under this article until the new street to be substituted for it, and which is specified in column (3) of Part 2 and 3 of that Schedule has been completed to the reasonable satisfaction of the highway authority and is open for use.
(4)
Where a street has been permanently stopped up under this article—
(a)
all rights of way over or along the street so stopped up shall be extinguished, and
(b)
(5)
(6)
This article is subject to paragraph 2 of Schedule 6 (provisions relating to statutory undertakers etc.) to this Order.