Power to deviate
6.—(1) In constructing or maintaining any of the scheduled works, Network Rail may—
(a)deviate laterally from the lines or situations shown on the deposited plans within the limits of deviation for that work shown on those plans; and
(b)deviate vertically from the levels shown on the deposited sections—
(i)in the case of Work Nos. 2A, 3, 3A, 3B, 4, 6, 7, 7A, 8, 9, 9A, 10, 10A, 10B, 10C, 11, 12, 13A, 13B and 14 to any extent not exceeding 0.75 metres upwards or downwards; and
(ii)in the case of any of the remaining works, to any extent not exceeding 3 metres upwards or downwards.
(2) In constructing or maintaining the temporary vehicular bridges referred to in article 28(2), Network Rail may deviate vertically from the levels shown on the deposited sections—
(a)in the case of the bridge referred to in article 28(2)(a), to any extent not exceeding 0.75 metres upwards or downwards; and
(b)in the case of the bridge referred to in article 28(2)(b), to any extent not exceeding 0.75 metres upwards.