The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004

Construction and maintenance of new or altered streetsE+W

13.—(1) Any street to be constructed under this Order shall be completed to the reasonable satisfaction of the highway authority and shall, unless otherwise agreed, be maintained by and at the expense of DLRL for a period of 12 months from its completion and at the expiry of that period by and at the expense of the highway authority.

(2) Where a street is altered or diverted under this Order, the altered or diverted part of the street shall when completed to the reasonable satisfaction of the street authority, unless otherwise agreed, be maintained by and at the expense of DLRL for a period of 12 months from its completion and at the expiry of that period by and at the expense of the street authority.

(3) Paragraphs (1) and (2) do not apply in relation to the structure of any bridge or tunnel carrying a street over or under any authorised railway.