The Docklands Light Railway (Woolwich Arsenal Extension) Order 2004

Articles 4, 21 and 30

SCHEDULE 10E+WLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

(1)(2)(3)(4)
AreaNumber of land shown on the deposited plansPurpose for which temporary possession may be takenAuthorised work
King George V Dock2, 12, 13, 14, 20Work sites, dock for spoil removalWorks Nos. 1, 2, 3 and 4
Within and adjacent to the River Thames93, 106, 107Work site and river accessWorks Nos. 5, 6, 7, 8 and 9
Land adjacent to Wellington Avenue, Woolwich Arsenal116, 119, 120, 123Work siteWork No. 1
Land adjacent to Plumstead Road130, 131, 132, 159, 160Work site for settlement mitigation works and for temporary replacement car parkingWork No. 1
Railway track and adjacent land206Site of a temporary railway platform and access rampWorks Nos. 10 and 12
Car Park to Greenwich Community College233Work site for settlement mitigation works and for temporary replacement car parkingWork No. 1
Part of Woolwich New Road274Traffic management for road re-alignmentWorks Nos. 17 and 18
Land adjacent to Beresford Street305Work site for sewer diversion worksWork No. 20