SCHEDULE 1RIVER BASIN MANAGEMENT PLANNING

Publication of information14

1

The Agencies must make accessible to the public at their principal offices—

a

the results of the work required by paragraph 1 (characterisation of river basin district);

b

maps showing bodies of water identified under paragraph 3 (bodies of water used for the abstraction of drinking water);

c

the register prepared under paragraph 4 (register of protected areas);

d

the results of the programmes established under paragraph 5 (monitoring);

e

the environmental objectives and programme of measures proposed or approved under paragraph 6 (environmental objectives and programme of measures); and

f

any supplementary plan prepared under paragraph 12 (supplementary plans).

2

Where the Ministers approve (with or without modifications) proposals made by the Agencies under paragraph 6(1), the Agencies must publish a notice—

a

stating that the proposals have been approved; and

b

specifying the arrangements made for making the approved objectives and programme of measures accessible to the public.

3

The Ministers must make accessible to the public through their websites and at their principal offices the results of the analysis conducted under paragraph 2 (economic analysis of water use in river basin district).

F14

The Ministers must ensure that, no more than three years after publication of an updated river basin management plan under paragraph 11—

a

an interim report is produced describing progress in the implementation of the planned programme of measures;

b

the report is published in such manner as the Ministers consider appropriate.