Prior investigation
94.—(1) Prior to the submission of plans pursuant to paragraph 95, the undertaker shall commission the company or such other body as the company acting reasonably may approve to undertake on behalf of the undertaker an investigation of any apparatus reasonably likely to be affected by the specified works.
(2) The investigation undertaken for the purposes of this paragraph will—
(a)include appropriate monitoring of flows in different conditions to establish the loading and capacity of sewers, drains and associated works forming part of such apparatus;
(b)have regard to the need to maintain existing services without any lowering in their performance and to the desirability of securing that sewers operate on the basis of gravity flows;
(c)identify such works to be designed by the undertaker as may be reasonably necessary for the alteration and protection of any apparatus which is the subject of such an investigation; and
(d)where undertaken by the company be carried out with all reasonable expedition on behalf of the undertaker and delivered to the undertaker together with all surveys, models, reports, monitoring data and the like used in the investigation upon its completion.