Capacity analysis

This section has no associated Explanatory Memorandum

24.—(1) Where required in accordance with regulation 23(4), the infrastructure manager must carry out a capacity analysis of the congested infrastructure in order to identify the reasons for the congestion and the measures which might be taken in the short and medium term to ease that congestion.

(2) In conducting the capacity analysis, and in order to identify the reasons for the congestion, the infrastructure manager must consider the—

(a)characteristics of the congested infrastructure;

(b)operating procedures used on that infrastructure; and

(c)characteristics of the different rail services which have been allocated capacity to operate on that infrastructure.

(3) In seeking to determine measures to alleviate congestion the infrastructure manager must consider, in particular—

(a)re-routing of services;

(b)re-timing of services;

(c)alterations to the line-speed; and

(d)infrastructure improvements.

(4) The infrastructure manager must consult the Secretary of State or, where any part of the capacity analysis relates to railway infrastructure in Scotland, Scottish Ministers, during the preparation of the capacity analysis.

(5) The infrastructure manager must complete the capacity analysis within six months from the date on which the infrastructure is declared to be congested in accordance with regulation 23(1) or (2) and make the findings of the analysis available to the parties described in regulation 23(3).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources