10. Where a well operation is to be carried out by means of a non-production installation or a vessel—
(a)particulars of—
(i)the meteorological and oceanographic conditions to which that installation or, as the case may be, vessel may foreseeably be subjected;
(ii)the depth of water; and
(iii)the properties of the sea-bed and subsoil
at the location at which the well operation will be carried out; and
(b)a description of how the well operator and—
(i)the owner of the installation; or
(ii)the operator and owner of the vessel
involved in the well operation will co-ordinate their management systems so as to reduce the risks from a major accident to comply with the relevant statutory provisions.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: