Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
18.—(1) Any consent granted under regulation 16(1) is to be subject to—
(a)the conditions in paragraph (2); and
(b)any other conditions Natural England thinks fit.
[F1(1A) Natural England may grant a consent subject to a condition which ensures that the applicant is under a duty to monitor the significant adverse effects of the significant project on the environment only if satisfied that the type of parameters to be monitored and the duration of monitoring are proportionate to the nature, location and size of the significant project and the significance of its effect on the environment.]
(2) The conditions required by paragraph (1)(a) are—
(a)the consent lapses if the project is not commenced (by the carrying out of a material act) within 1 year of the date on which it was granted;
(b)the consent expires if the project is not completed within 3 years of the date on which it was granted; and
(c)the consent only authorises the project described in the consent application, subject to any amendments approved by Natural England under paragraph (4).
(3) After the expiry of a consent in accordance with paragraph (2)(b), Natural England may require a further application for consent in accordance with paragraph (5) in respect of any further operations or uses forming part of the project.
(4) Natural England may approve any amendments at the request of an applicant, but any material change in the authorised operations or uses requires a further application for consent in accordance with paragraph (5).
(5) Further applications for consent under paragraphs (3) and (4) may be subject to any requirement of these Regulations that Natural England considers appropriate.
(6) In this regulation, a project is “completed” if all the works permitted by the consent have been carried out and all changes in the use, or the level of use, of the relevant land have been implemented.
Textual Amendments
F1Reg. 18(1A) inserted (16.5.2017) by The Environmental Impact Assessment (Agriculture) (England) (No. 2) (Amendment) Regulations 2017 (S.I. 2017/593), regs. 1(1), 13 (with reg. 19)
Commencement Information
I1Reg. 18 in force at 10.10.2006, see reg. 1(2)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: