The Luton Dunstable Translink Order 2006

Temporary use of land for construction of works

24.—(1) The Council may, in connection with the carrying out of the authorised works—

(a)enter upon and take temporary possession of the land specified in columns (1) and (2) of Schedule 8 (land of which temporary possession may be taken) to this Order for the purpose specified in relation to that land in column (3) of that Schedule relating to the authorised works specified in column (4) of that Schedule,

(b)remove any buildings and vegetation from that land, and

(c)construct temporary works (including the provision of means of access) and buildings on the land.

(2) Not less than 28 days before entering upon and taking temporary possession of land under this article the Council shall serve notice of the intended entry on the owners and occupiers of the land.

(3) The Council may not, without the agreement of the owners of the land, remain in possession of any land under this article after the end of the period of one year beginning with the date of completion of the work or works specified in relation to that land in column (4) of Schedule 8 (land of which temporary possession may be taken) to this Order.

(4) Before giving up possession of land of which temporary possession has been taken under this article, the Council shall remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the Council shall not be required to replace a building removed under this article.

(5) The Council shall pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.

(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, shall be determined under Part 1 of the 1961 Act.

(7) Without prejudice to article 53 (no double recovery), nothing in this article shall affect any liability to pay compensation under section 10(2) of the 1965 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (5).

(8) Subject to paragraphs (9) and (10), the powers of compulsory acquisition of land conferred by this Order shall not apply in relation to the land referred to in paragraph (1).

(9) The Council shall not be precluded from acquiring new rights over any part of that land under article 22 (power to acquire new rights).

(10) Where the Council takes possession of land under this article, it shall not be required to acquire the land or any interest in it.

(11) Section 13 of the 1965 Act shall apply to the temporary use of land pursuant to this article to the same extent as it applies to the acquisition of land under this Order by virtue of article 20(1) (application of Part 1 of the Compulsory Purchase Act 1965).

(12) In this article “building” includes structure or any other erection.