The Marine Works (Environmental Impact Assessment) Regulations 2007

[F1Consultation on proposed regulated activityU.K.

This section has no associated Explanatory Memorandum

17.(1) The appropriate authority must [F2as soon as reasonably possible] either—

(a)supply the following material to such of the consultation bodies as it considers appropriate—

(i)a copy of the application;

(ii)a copy of the environmental statement;

(iii)a copy of any further information supplied by the applicant to the appropriate authority; and

(iv)a letter stating that any representations in response to consultation regarding the application should be made in writing to the appropriate authority, at an address specified by the appropriate authority, within 42 days from the date of the letter (or such longer period as may be agreed between the consultation body and the appropriate authority in accordance with paragraph (2)); or

(b)direct the applicant to do so.

(2) The appropriate authority may agree a longer consultation period with a consultation body where, in the opinion of the appropriate authority, it is reasonable to do so.

(3) Neither the regulator nor the appropriate authority need deal further with, or exercise any functions under these Regulations in relation to, the application, and the regulator must not reach its regulatory decision, until the applicant has complied with any direction made in accordance with paragraph (1)(b).

(4) Where the applicant has failed to comply with a direction made in accordance with paragraph (1)(b) within such reasonable period as the appropriate authority has specified, or such longer period as the appropriate authority may reasonably allow—

(a)the regulator may treat the application as having been withdrawn, and

(b)the appropriate authority (if the regulator is not also the appropriate authority) may direct the regulator to do so.

(5) Neither the regulator nor the appropriate authority need deal further with, or exercise any functions under these Regulations in relation to, the application, and the regulator must not reach its regulatory decision, until the consultation period (including any extension agreed in accordance with paragraph (2)) has expired.]