PART 2CONSERVATION OF NATURAL HABITATS AND HABITATS OF SPECIES

Plans and projects

Co-ordination where more than one competent authority is involved29

1

The following provisions apply where a plan or project—

a

is undertaken by more than one competent authority;

b

requires the consent, permission or other authorisation of more than one competent authority; or

c

is undertaken by one or more competent authorities and requires the consent, permission or other authorisation of one or more other competent authorities.

2

Nothing in regulation 25(1) or 27(3) requires a competent authority to assess any implication of a plan or project which would be more appropriately assessed under that provision by another competent authority.

3

The Secretary of State may issue guidance to competent authorities for the purposes of regulations 25 to 28 as to the circumstances in which an authority may or should adopt the reasoning or conclusions of another competent authority as to whether a plan or project—

a

is likely to have a significant effect on a European offshore marine site or European site; or

b

may adversely affect the integrity of a European offshore marine site or European site.

4

A competent authority must have regard to any guidance issued by the Secretary of State under paragraph (3) in discharging any of its functions under regulations 25 to 28.

5

In determining whether a plan or project should be agreed to under regulation 26(1), a competent authority other than the Secretary of State must seek and have regard to the views of any other competent authority or authorities involved.

6

The Secretary of State may not issue any guidance under paragraph (3) which relates to a function within devolved competence without the consent of the Scottish Ministers.