24. Not later than 28 days before—
(a)starting to carry out any tidal work; or
(b)exercising any of the powers conferred by article 9 (power to dredge etc.),
the Council shall submit to the Port Health Authority plans thereof and such further particulars as may be available to the Council and as the Port Health Authority may reasonably require in respect of carrying out such works or in exercising such powers.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: