2.—(1) Not later than 28 days before—
(a)starting to carry out any tidal works; or
(b)exercising any of the powers of article 9 (power to dredge etc.),
the Council shall submit to the Port Authority plans thereof and such further particulars as may be available to the Council and as the Port Authority may reasonably require and in carrying out such works or in exercising such powers, the Council shall comply with all reasonable modifications and conditions (not involving alteration to the basic design of any tidal works) required by the Port Authority, including protective works.
(2) Any modifications or conditions referred to in sub-paragraph (1) shall be notified by the Port Authority to the Council within 28 days of the receipt by the Port Authority of the plans or particulars to which such modifications or conditions relate.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: