12. No more than 167,000m2 of B1(b), B1(c), B2 and B8 development and the Ro-Ro or, alternatively, 1 berth without the Ro-Ro, shall be first occupied or brought into beneficial use prior to the completion of the construction of acoustic barriers where appropriate—
(a)along either side of The Manorway from its junction with the A13 to the new Sorrells roundabout;
(b)along the northern section of the new access road;
(c)along either side of the A13 from where it meets Stanford Road immediately west of the junction of Stanford Road and Buckingham Hill Road north-eastwards to the point north of Caldwell Road; and
(d)along the south side of the A13 from a point north of Hemley Road to the junction with Saffron Gardens,
in each case as approved by the appropriate authority and in conformity with Highways Agency Standard HA 66/95 “Environmental Barriers Technical Requirements” (or any standard which may replace it).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: