Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
7.—(1) Subject to paragraphs (4) and (5), the Mayor may give to the local planning authority a direction under section 2A of the 1990 Act if he considers that—
(a)the development or any of the issues raised by the development to which the PSI application relates is of such a nature or scale that it would have a significant impact on the implementation of the spatial development strategy;
(b)the development or any of the issues raised by the development to which the application relates has significant effects that are likely to affect more than one London Borough; and
(c)there are sound planning reasons for issuing a direction.
(2) The direction must state that the Mayor is to act as the local planning authority for the purpose of—
(a)determining the application; and
(b)where relevant, determining any connected application.
(3) In deciding whether to give a direction the Mayor must take account –
(a)where the application relates to development which falls within Category 1A of the Schedule, of the extent to which the council of the London Borough in which the development is or is to be situated is achieving, and has achieved the applicable development plan targets for new housing, including affordable housing;
(b)in relation to all applications, of the extent to which the council of the London Borough is achieving, and has achieved any other targets set out in the development plan which are relevant to the subject matter of the application.
(4) Where an application for development which falls within Category 1A of the Schedule is referred to the Mayor, paragraph (1)(b) does not apply.
(5) A direction must be given either—
(a)within the period referred to in article 5(1)(b)(i); or
(b)where paragraph (6) applies, within 14 days of receiving the applicant's request .
(6) This paragraph applies where—
(a)the authority has failed to provide the statement referred to in article 5(1)(a)(iii) within the relevant period specified in article 20(2) of the GDPO; and
(b)the applicant has requested the Mayor in writing to give a direction under section 2A of the 1990 Act.
(7) In giving reasons for making a direction the Mayor must specify how the matters set out in paragraph (3) have affected his decision.
(8) A local planning authority must place on Part 2 of the register required to be kept by article 25 of the GDPO (register of applications) a copy of any direction it receives under this article within 14 days of receiving it.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: