18.—(1) Paragraphs (2) and (3) apply where the responsible person in relation to a tolling arrangement is not an appropriate national authority, and [F1an infrastructure charge tolling arrangement]

(a)comes into effect after the date these Regulations come into force, and

(b)does involve a concession toll.

(2) Where this paragraph applies, the responsible person must communicate to the appropriate national authority the following information—

(a)details of the concession contract under which the concession toll is levied, or significant changes to such contracts, and

[F2(b)the base case on which the grantor under the concession contract has founded the concession notice within the meaning of regulation 6 of the Concession Contracts Regulations 2016.]

(3) The base case referred to in paragraph (2)(b) must include—

(a)an estimate of the costs referred to in regulation 4(1) in relation to the concession,

(b)a forecast of the traffic divided into types of HGV,

(c)the levels of tolls envisaged, and

(d)the geographic extent of the network covered by the concession contract.

F3(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F3(5) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

F4(6) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .