PART 3 E+WFLOOD HAZARD MAPS AND FLOOD RISK MAPS

[F1Review: appropriate agency] E+W+S

23.—(1) The [F2appropriate agency] must review each flood hazard map and each flood risk map prepared by it under regulation 18.

(2) Following a review, the [F3appropriate agency] may prepare—

(a)a revised flood hazard map;

(b)a revised flood risk map.

(3) The first review must be completed before 22nd December 2019.

(4) Subsequent reviews must be carried out at intervals of no more than 6 years.

(5) The [F4appropriate agency] must, so far as is reasonably practicable, co-ordinate a review under this regulation with a review of a river basin district under regulation 5(2) of the Water Environment Regulations.