The Flood Risk Regulations 2009

 Help about what version

What Version

 Help about opening options

Opening OptionsExpand opening options

Status:

This is the original version (as it was originally made).

Review: Environment Agency

This section has no associated Explanatory Memorandum

23.—(1) The Environment Agency must review each flood hazard map and each flood risk map prepared by it under regulation 18.

(2) Following a review, the Agency may prepare—

(a)a revised flood hazard map;

(b)a revised flood risk map.

(3) The first review must be completed before 22nd December 2019.

(4) Subsequent reviews must be carried out at intervals of no more than 6 years.

(5) The Agency must, so far as is reasonably practicable, co-ordinate a review under this regulation with a review of a river basin district under regulation 5(2) of the Water Environment Regulations.