Generating stations which were accredited, or held preliminary accreditation, as at 31st March 2009

This section has no associated Explanatory Memorandum

31.—(1) This article applies to a generating station—

(a)which was accredited as at 31st March 2009;

(b)which has not ceased to be accredited since that date; and

(c)to which articles 28 to 30 do not apply.

(2) This article also applies to a generating station—

(a)which was accredited on or before 31st March 2011;

(b)which, since being accredited, has not ceased to be accredited at any time;

(c)in respect of which preliminary accreditation was held—

(i)as at 31st March 2009, and

(ii)from that date until the date on which the station was accredited; and

(d)to which articles 28 to 30 do not apply.

(3) Subject to paragraphs (4) to (6), the amount of electricity to be stated in each ROC issued in respect of electricity generated by a generating station to which this article applies is to be determined in accordance with article 27(4) and (5).

(4) Where the electricity generated by a generating station to which this article applies is generated in a way described in the first column of Part 4 of Schedule 2, the amount of electricity to be stated in each ROC issued in respect of that electricity is (subject to paragraph (5)) the amount which corresponds to that description in the second column of that Part of that Schedule.

(5) Where, at any time it generates electricity after 31st March 2011, the generating station’s total installed capacity is greater than it was on 31st March 2011, paragraph (4) applies only in relation to ROCs which are to be issued in respect of—

(a)where electricity generated using the total installed capacity of the station as at 31st March 2011 (“the original capacity”) is measured separately from electricity generated using capacity which has been added to the station since that date, the electricity which is generated using the station’s original capacity;

(b)in any other case, the appropriate percentage of the electricity generated by the station (the appropriate percentage for these purposes being the total installed capacity of the station as at 31st March 2011 expressed as a percentage of the total installed capacity of the station as at the date of generation of the electricity).

(6) In relation to the remainder of the electricity generated by the generating station, the amount of electricity to be stated in each ROC is to be determined in accordance with article 27(4) and (5).

(7) This article is subject to article 32.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources