PART 6APPROVAL OF BATTERY COMPLIANCE SCHEMES

Further information in respect of an application48

1

The appropriate authority may, if it considers that it requires further information to determine an application, serve a notice on the applicant specifying—

a

the information required; and

b

the date by which it is required (being the date mentioned in paragraph (3)).

2

The appropriate authority must serve any notice under paragraph (1)—

a

in respect of an application made under regulation 47(1)—

i

in respect of the first compliance period, on or before 30th June 2009;

ii

in respect of any other compliance period, on or before 15th June of the year before that compliance period;

b

in the case of an application made in reliance on regulation 47(3), within 28 days of the date of receipt of the application.

3

The applicant must provide the information not later than—

a

31st August in the year before the compliance period in respect of which the approval is to take effect; or

b

in the case of an application made in reliance on regulation 47(3), within 42 days of the date of the notice.